Engineering capabilities

What ATS has actually delivered, to which standards and by which process. We only list what we can show through projects and handover documents.

Figures from the ATS capability profile, including the team's experience before the company was founded.

Scope

From sensor to management report

Organised on the ISA-95 layer model used by multinational manufacturers.

Level 4 · ERPPlanning, inventory, costing, accountingData integration
Level 3 · MES / OEEOutput, downtime, OEE, batch traceability, Andon, shift reports✓ ATS delivers
Level 2 · SCADA / HMIOperator screens, monitoring, alarms, data logging✓ ATS delivers
Level 1 · PLC / controlProgramming, upgrades, safety PLC, VFDs, servo✓ ATS delivers
Level 0 · Devices & powerPanels, sensors, motors, energy metering, industrial networks✓ ATS delivers
Platforms

Brands and controller families we have worked on

Hands-on programming and configuration in real projects. ATS only uses the word "partner" with a brand when officially certified.

MitsubishiFX1N · FX3U · FX5U · Q series (Q03)Filling, capping and mixing lines; RS-232/485 communication
SiemensS7-300Filling machines, case feeding, product orientation
ABBAC500 PLC · ABB drivesPalletising robot
BeckhoffCX5100Embedded controller
Networks & dataModbus RTU/TCP · industrial EthernetPlant Wi-Fi, fibre, IoT gateways, databases
Standards

Built to standards, fully documented

Panels

Designed with reference to IEC 61439, routine-tested before delivery, labels and diagrams inside the panel

Production data

Structured on ISA-95; OEE to the standard definition (availability × performance × quality)

Handover documents

I/O lists, as-built drawings, backed-up PLC/HMI programs, operating instructions in Vietnamese

Confidentiality

NDA on every project; programs and data belong to the client

ATS does not provide GxP / pharmaceutical validation services.

Delivered on site

Photos taken on site with client names and logos removed. More on the Projects page →

Project process

7 steps, with a factory acceptance test before we enter your plant

1SurveyCurrent state, program backup, panel photos, I/O list
2DesignDrawings, bill of materials, scope, schedule – approved by the client
3Build & programPanel wiring, PLC program, HMI screens
4FAT at ATS workshopSimulated test run; the client may attend
5InstallationWithin the agreed shutdown window, with a rollback plan
6SAT & acceptanceTest under load, acceptance record, training
7MaintenanceAMC contract, periodic backups, remote support

Step 4 (FAT) makes the difference: panels and programs are tested at the ATS workshop first, so downtime at your plant is short and low-risk.

Site safety

Working to FDI plant safety rules

  • Permit to work and risk assessment for every task
  • Isolation, lockout–tagout (LOTO) before any work
  • Work at height: harness, certified ladders, health checks as required
  • PPE and tool checklists before entering the plant
  • Compliance with the client's supplier code of conduct
Coverage

Ho Chi Minh City and nearby industrial parks

Office in Ho Chi Minh City, with projects delivered in industrial parks in Binh Duong and Dong Nai. Remote support for connected systems; remote engineering services for overseas clients.

Download the capability profile (PDF)

4 pages: capabilities, the 5 layers ATS delivers, PLC platforms, standards, site safety, selected projects (client names withheld). Prefer a quick on-screen view? 3-minute slides.

See what we have delivered

Problem → solution → result, written from real projects.

See projects