For clinics, cold storage and plants that run continuously, a few minutes without power can ruin an entire batch. An ATS (Automatic Transfer Switch) panel transfers to the generator automatically when grid power is lost and returns when power is back. Here are the points to ask about when ordering one.
1. Rated current
Size it to the load current to be supplied from the generator (not the whole plant load), plus allowance for expansion. Common ratings: 63A, 100A, 160A, 250A, 400A, 630A and above.
2. Switching device: contactor, MCCB or ACB
- Contactor: cheap, fast transfer, suited to small to medium loads.
- Motorised MCCB: switches and protects, common for 100–630A.
- ACB: for large currents, the plant's main panel.
- Or a manufacturer's integrated transfer switching equipment (ATSE) – compact, with an interlock built in.
3. 3-pole or 4-pole
Whether the neutral also needs to be switched depends on how the grid and generator systems are earthed. This is a technical decision that needs an engineer to look at the actual diagram, so do not choose by price.
4. Interlock
Mechanical and electrical interlocks are mandatory so that the two sources are never closed at the same time, to avoid back-feeding generator power onto the grid (dangerous for utility linemen) or short-circuiting the sources.
5. Time delays
- Generator start delay (to ride through flickers of a few seconds).
- Load transfer delay after the generator voltage and frequency stabilise.
- Return-to-grid delay once grid power is stable again.
- Generator cool-down time before shutdown.
6. Voltage and phase-loss monitoring
In many industrial zones, power does not fail completely but sags or loses one phase – motors burn out running on unbalanced phases. The controller should detect voltage sag, phase loss and wrong phase sequence.
7. Remote monitoring and logs
Alerts via Zalo/SMS on grid loss, generator running and failed transfer; keep a log of the number and duration of outages for dealing with the utility and for calculating generator diesel cost.