The 6 Big Losses in OEE: Where Your Machines Lose Time and Which to Fix First

OEE & production data · 2 min read · Updated 13 Nov 2026 · ATS Vietnam engineering team

OEE (overall equipment effectiveness) tells you what percentage of its potential a machine is actually delivering. But a single OEE number does not tell you what to fix. To know that, break OEE down into the 6 big losses, a split long used in total productive maintenance (TPM).

Six losses, grouped into the three OEE factors

OEE factorLossHow to recognise it on the line
Availability
is the machine running?
1. BreakdownsMachine stops from mechanical or electrical failure, waiting for a technician, waiting for spare parts
2. Changeover and setupStops to change a mold, switch product, or adjust the machine until it produces good parts
Performance
is it running fast enough?
3. Minor stopsJammed workpieces, false sensor alarms, operator intervention for a few dozen seconds, repeated many times per shift
4. Reduced speedMachine runs below standard cycle time because "running fast causes defects", the machine is worn, or the material is difficult
Quality
are the parts good?
5. Production defectsScrap and rework while the machine is running steadily
6. Start-up scrapBad parts at the start of a shift, after a changeover, or after a long stop

How to log data when you have no software yet

  • Downtime log for team leaders: start time, end time, reason (chosen from a ready-made list), for every stop of 3 minutes or more.
  • End of shift: total output, number of defective parts, planned run time.
  • Standard cycle time (seconds per product) for each product code: take it from the machine design or from the best cycle time reliably achieved.
  • Enter it in Excel every day; after 2 weeks, add up lost time by reason and rank from largest to smallest.

Minor stops and reduced speed are usually not logged, but they show up as low performance: plenty of run time, but output that does not match it.

What to fix first

  1. Take the biggest loss by hours, not by feeling. Usually 2–3 reasons account for more than half of the downtime.
  2. Start with cheap, quick fixes: prepare molds and materials before stopping the machine for a changeover, feed material on a schedule, clean sensors that give false alarms.
  3. Repeat breakdowns in the same assembly → move it into preventive maintenance and keep spare parts.
  4. Reduced speed: ask why it does not run at the standard cycle time; often it is because of fear of quality defects, so the root cause has to be handled in quality.
  5. Measure again after 2–4 weeks to see the result in numbers.

How ATS does this

With the 2-week machine loss survey, ATS works with your team leaders to log data exactly as above, then hands back a 1-page report: OEE per machine, hours lost each week, stop reasons ranked by lost time, and the 3 things to do first. To calculate quickly yourself, use the OEE calculator; to understand how it is calculated, read What is OEE.

For reference only. Work on energised panels requires qualified, safety-trained personnel. ATS inspections do not replace the statutory inspection required for equipment subject to it under Vietnamese regulations.

Frequently asked questions

What is a good OEE?

85% is often quoted as world class for high-volume manufacturing, but it varies by industry. What matters more is whether your own line's OEE is rising or falling month by month, and which loss is currently the biggest.

How do I measure OEE without software?

Give team leaders a downtime log (start time, end time, reason) and record output per shift in Excel. Two weeks is enough to see which loss is the largest.

Do I need to log stops of just a few dozen seconds?

Not by hand, it is not practical. Usually you log stops of 3 minutes or more, and minor stops show up as low performance. To see minor stops clearly, you need an automatic logger attached to the machine.