OEE (overall equipment effectiveness) tells you what percentage of its potential a machine is actually delivering. But a single OEE number does not tell you what to fix. To know that, break OEE down into the 6 big losses, a split long used in total productive maintenance (TPM).
Six losses, grouped into the three OEE factors
| OEE factor | Loss | How to recognise it on the line |
|---|---|---|
| Availability is the machine running? | 1. Breakdowns | Machine stops from mechanical or electrical failure, waiting for a technician, waiting for spare parts |
| 2. Changeover and setup | Stops to change a mold, switch product, or adjust the machine until it produces good parts | |
| Performance is it running fast enough? | 3. Minor stops | Jammed workpieces, false sensor alarms, operator intervention for a few dozen seconds, repeated many times per shift |
| 4. Reduced speed | Machine runs below standard cycle time because "running fast causes defects", the machine is worn, or the material is difficult | |
| Quality are the parts good? | 5. Production defects | Scrap and rework while the machine is running steadily |
| 6. Start-up scrap | Bad parts at the start of a shift, after a changeover, or after a long stop |
How to log data when you have no software yet
- Downtime log for team leaders: start time, end time, reason (chosen from a ready-made list), for every stop of 3 minutes or more.
- End of shift: total output, number of defective parts, planned run time.
- Standard cycle time (seconds per product) for each product code: take it from the machine design or from the best cycle time reliably achieved.
- Enter it in Excel every day; after 2 weeks, add up lost time by reason and rank from largest to smallest.
Minor stops and reduced speed are usually not logged, but they show up as low performance: plenty of run time, but output that does not match it.
What to fix first
- Take the biggest loss by hours, not by feeling. Usually 2–3 reasons account for more than half of the downtime.
- Start with cheap, quick fixes: prepare molds and materials before stopping the machine for a changeover, feed material on a schedule, clean sensors that give false alarms.
- Repeat breakdowns in the same assembly → move it into preventive maintenance and keep spare parts.
- Reduced speed: ask why it does not run at the standard cycle time; often it is because of fear of quality defects, so the root cause has to be handled in quality.
- Measure again after 2–4 weeks to see the result in numbers.
How ATS does this
With the 2-week machine loss survey, ATS works with your team leaders to log data exactly as above, then hands back a 1-page report: OEE per machine, hours lost each week, stop reasons ranked by lost time, and the 3 things to do first. To calculate quickly yourself, use the OEE calculator; to understand how it is calculated, read What is OEE.