Every year-end, plants run at full capacity and then shut down for many days at Tet. That is when electrical panels carry their heaviest load of the year and are then left unattended the longest. According to the Fire Prevention and Rescue Police Department (Ministry of Public Security), nearly 63% of fires nationwide in 2020–2024 were caused by electrical systems and equipment (Saigon Giai Phong newspaper, 23 April 2025). This article is a practical list for plant, EHS and maintenance managers in Binh Duong, Dong Nai and Ho Chi Minh City.

Why electrical faults turn into fires

Most are not a sudden "short circuit". They are faults that build up over time:

  • Loose terminations and busbar joints: contact resistance rises and the joint heats up until the insulation burns.
  • Prolonged overload: cables, breakers and contacts run near or beyond their rating after overtime shifts or added machines.
  • Dust and moisture: dust reduces cooling and creates leakage paths; moisture causes surface discharge.
  • Aging power-factor capacitors: swollen or overheated capacitors, or a failed controller, can become a heat source inside the panel.

Many factory fires in industrial parks were reported in the press in 2025. Each has its own cause and the investigation belongs to the authorities, so this article does not speculate on individual cases. The general lesson is that plants should proactively check their own electrical systems.

Why do it before Tet

  • Highest load of the year in December exposes loose joints and overloads. It is the time when thermal imaging gives the clearest results.
  • Long shutdown, nobody on site: a small fault can develop for days without being noticed.
  • Re-energizing after the break creates simultaneous starting currents that test the weakest joints.

The legal side

The Law on Fire Prevention, Fighting, Rescue and Relief No. 55/2024/QH15 was passed by the National Assembly on 29 November 2024 and took effect on 1 July 2025. It includes provisions on fire safety in installing and using electricity. Plants should check the original text and current guidance with their fire-safety consultant.

10 things to do before the shutdown

  1. Thermally scan main panels, distribution panels, MCCs and capacitor panels at high load, recording the load current at measurement.
  2. Fix the hot spots found: retighten terminations, replace worn contacts, then rescan to confirm.
  3. Clean the panels once safely de-energized: vacuum dust, check fans, filters and door seals.
  4. Check capacitor banks: swollen or discolored capacitors, controller fault alarms.
  5. Review overloads: compare actual current with breaker and cable ratings, especially after adding machines.
  6. Check earthing and protective conductors on key panels and machines.
  7. Clear combustibles around panels, electrical rooms and generators: pallets, cardboard, chemicals.
  8. Test the generator and ATS panel under load (see how to choose an ATS panel).
  9. List the loads to switch off and the loads to keep, with a named person responsible for each.
  10. Keep records: thermal images, work done, who did it, date.

A more detailed list is in the article electrical panel inspection checklist for factories. If you want to do a first review yourself, use the electrical panel self-check tool.

What thermal imaging finds

A thermal camera sees abnormal hot spots while the panel is still running: loose terminations, worn contacts, one phase hotter than the others, overloaded cables. The key condition is that the measurement must be done under load. A panel at rest or lightly loaded can give a "clean" image even if a joint is already loose. How to read the results is in how to read thermal images of electrical panels, and the service itself is on the page thermal camera inspection of electrical panels.

Thermal imaging helps find problems early. It does not replace statutory inspection or periodic testing under regulations and cannot remove every risk.

During the break: what to switch off, what to keep

GroupWhat to do
Production lines, compressors, auxiliary machinesIsolate at the distribution panel in sequence, recording who switches off and who switches on again
Lighting, office air-conditioning, forklift chargersSwitch off completely; do not charge unattended
Fire protection, fire alarm, cameras, cold rooms, serversKeep powered; check backup supply and UPS
Generator and ATS panelLeave in automatic mode, with someone checking on a schedule during the break

Restart checklist after Tet

  1. Visually inspect electrical rooms and panels: burning smell, discoloration, water or insects.
  2. Energize in order from the main panel down to distribution panels, small loads first and large motors last, not all at once.
  3. Watch current, voltage and noise during the first hours.
  4. Do a quick rescan of the main panels after a few days at load to catch new loose joints.

How ATS helps

ATS thermally scans electrical panels while the plant is running and writes a report with repair priorities. If you want a broader view, a one-day factory survey gives you an overall picture of the plant's current condition in one report. ATS is not a statutory inspection body and does not replace statutory inspection.

For reference only. Work on energised panels requires qualified, safety-trained personnel. ATS inspections do not replace the statutory inspection required for equipment subject to it under Vietnamese regulations.

Frequently asked questions

When should we do thermal imaging before Tet?

Do it while the plant is running at high load, usually in December, so there is still time to fix hot spots before the shutdown. A panel with no load will not show a loose connection on a thermal image.

Should we cut all power during the Tet shutdown?

Not necessarily. Switch off the panels and loads you do not need, but keep what must run continuously, such as fire protection, cameras, cold rooms or servers. List what stays on clearly and have someone on duty or monitoring remotely.

Does thermal imaging replace fire-safety inspection by the authorities?

No. Thermal imaging is a maintenance check by the plant. It does not replace statutory inspection, design review or acceptance under regulations. Plants should check current requirements with their fire-safety consultant.